Re-roofing
The City of Pasadena has adopted Chapter 32 of the Uniform Building Code Appendix
as a building standard for re-roofing. These guidelines are contingent upon some
discretion on the part of the building official. The following standard policies are set
forth to allow consistency. These policies do not void any requirements in the Appendix,
but serve as clarification only.Installation of wood
or asphalt shingles requires only a final inspection.
Built-up roofs must be removed to allow the existing roof
sheathing to be inspected. Rotting is a common and may not adequately provide support for
the new roof barrier. Final inspection is also required.
All roofing underlayment and interlayment must be ASTM
approved material.
Metal roofs will require an underlayment on listed Manville
1-1/2 inch thick foil faced fiberglass bath insulation installed with the foil face up and
2 inch head laps over the existing roof surface prior to the battening system. A battening
and insulation inspection is required.
Roofing with any tile weighing more than six pounds
per square foot (6PSF) will require engineering calculations addressing the additional
loads imposed upon the roof structure. The engineer must also note that the entire
structure is adequate to sustain the additional loads, regardless if the original is torn
off or not.
Roofs requiring engineering calculations shall have
submitted with calculations a dimension roof plan. An inspection of the roof is required
(regardless if structural modifications are necessary) at a time the roofing material is
torn off and before the solid sheathing is applied.
Roofs installed with a tile weighing 6.0 PSF
or less will require a copy of the material receipt at the time of final inspection.
Receipt requires to have the job address on the receipt.
If plywood is removed and replaced, nailing
shall be inspected to ensure equivalent strength to the roof diagram. This means
equivalent nail size and spacing as well as sheathing grade and thickness must be equal to
what is existing. If plywood is added over space sheathing, a nailing inspection will not
be required. Final inspection is always required.
NOTE
All roof finals shall require a ladder;
contractor to supply ladder
|